Project Description
Project engineer/manager. Design of pH control system and sequencing batch reactor system for treatment and discharge of winery process wastewater to native forested area. Design and construction were fast-tracked. Coordinated directly with suppliers for purchase and delivery of long lead/critical owner-furnished equipment (e.g., SBR, sludge and reclaimed water tanks, SBR and aeration equipment, pumps). Acted as the construction manager and coordinated contractors and the construction to fast-track and facilitate construction of the facilities prior to the upcoming crush. The facilities were operational prior to crush. Prepared a comprehensive O & M manual.
Project Details
Categories | |
Location | St. Helena, CA |